「Project News」〡Pakistan Lucky Seawater Desalination Plant Project Periodic Taking-over Test Passed Successfully

Time: 2021-08-20 11:03:34

Click:

On August 12th, 2021, Pakistan Lucky 1x660 MW Coal-fired Power Plant 16000m3/d Seawater Desalination Project have operated stably for more than 100 days. The operating working conditions of all the sub-systems of seawater desalination plant are all normal with qualified product water, moreover, all the parameters meet the requirement of technical specification, which is witnessed as the successful passing of periodic taking-over test.



Although the epidemic situation of Pakistan is rather critical, the site service Engineer Li Yabo insisted to work on site under the premise of following strictly the scientific control and management measures from EPC Contractor so that the commissioning work of seawater desalination system could be implemented as scheduled, as result, the commissioning and taking-over objectives were all fulfilled efficiently with high mark by the full assistance from China technical team and project management team. All the resources were arranged overall and efficiently to ensue the critical commissioning item be completed successfully.



▲Pakistan Lucky Seawater Desalination Plant


▲ Pakistan Lucky Project DM Water Workshop


The successful passing though of taking-over test of this project with qualified product water provided important guarantee to the water security of the whole project, and laid a solid foundation for the issue of final performance acceptance certificate.




Seawater desalination is one of the primary businesses of GREENISM water segment, and the application of sweater desalination technology on various industries and fields is being focused by GREENISM all the time. Several seawater desalination projects were conducted successfully in some regions of home and abroad. The passing thought of periodic taking-over test of Pakistan Lucky Coal-fired Seawater Desalination plant marked the complying of performance with technical specification, meanwhile exhibited the mission of GREENISM once again to conduct elite project, to fulfill the Clients’ dreams and to promote the living environment. GREENISM will adhering to the mission continuously to dig deeper in the field of environment project to fight for becoming the leading company trusted and respected by the Clients!

0
图片展示

Contact Us

Shandong Greenism Environmental Protection Technology Co.,Ltd

Add:No. 9266 Jiankang Dong Road, High-tech District, Weifang, Shandong     

Tel: +86 536-3955900 

Greenism New Water Co.,Ltd.

Add:NO.1 International Innovation Park,Keyuan Weiyi Road,Laoshan District,Qingdao,Shandong Province
Tel: +86 532-88701980

E-mail: sdgreenism@163.com

WECHAT OFFICIAL ACCOUNT

Service Center

Please choose online customer service to communicate

Contacts
Shandong Greenism Environmental Protection Technology Co., Ltd
0536-7908798
GREENISM WATER CO.,LTD
0532-88701980
Scan a QR Code
Add WeChat friend to learn more about the product
Use Enterprise WeChat
"Scan" to join the group chat
Copy success!
Add WeChat friend to learn more about the product
I see.